Replacement of gland expansion joints on hot water piping from the Mělník Power Plant to the Třeboratice Heating Plant
07/08/19

I&C Energo has signed a contract for the replacement of five outgoing DN1200 double-sided gland expansion joints on the hot water pipeline manifold, on its seventh and eighth sections near the municipalities of Chlumín - Obříství and Kojetice.
The work, the aim of which is to ensure problem-free and economical operation of the hot water piping, is planned for the summer outage of the hot-water piping and will be subsequently handed over to the customer (ČEZ Teplárenská, a.s.) including all the required documentation by the end of August 2019.