Modifications to Unit 6 equipment at the Ledvice Power Plant
06/08/19
During the current outage, I&C Energo a.s. is implementing several orders related to modifications to Unit 6 equipment at the Ledvice Power Plant.
Unit 6 is the only supercritical unit in the Czech Republic. It was put into operation in 2017 and our company participated significantly in its construction. Thanks to our experience in construction, we are involved in a number of works to improve both unit and non-unit equipment. The orders include design, material delivery and complete assembly. We are currently preparing orders for non-unit equipment for the next period.