Installation of the 3rd cooling pump of the spent fuel pool in the Dukovany NPP
On the basis of a contract for work signed in July 2017, I&C Energo a.s. is implementing the project "7129 - Installation of the 3rd cooling pump of the spent fuel pool" in the Dukovany NPP for ČEZ ENERGOSERVIS, spol. s r.o., electrical and I&C sections.
The purpose of the complete work is the implementation of the third division of the spent fuel pool cooling system for units 1 to 4. The completed cooling system will consist of a new pump powered by secured power supply 2nd category, EW controlled from the Control room and Emergency control room, and a new cooler connected to the VF 40.
The subject of our part of the work is the complete realization of electrical and I&C parts, i.e. delivery of components and documentation, assembly and execution of all necessary tests of the equipment including its commissioning in the electrical and I&C sections. The subject of the work is subject to the requirements of the new Atomic Act No. 263/2016 and Decree No. 358/2016 Coll. on requirements for quality assurance and technical safety and assessment and verification of conformity of selected equipment, as amended - safety class BT2 electrical part.
The addition of the new spent fuel pool cooling division, including related modifications in the B37 panel and the PCS system, also affects the full-range trainer